Aerial Control 2020-21
Please scroll down to see more information about each project listed below.
- Aorere
- St Arnaud
- Buller South
Quick link: Completed Aerial Operations
2020/21 Aorere Aerial
Client: Department of Conservation
Status: This operation has been split into eastern and western blocks which may be delivered at different times. Refer table below for status of each block. |
Eastern block |
Western block |
Non-toxic prefeed application in the eastern portion of the Aorere project area was completed 27/07/2020. 1080 application in the eastern portion of the Aorere project area was completed on 16/08/2020 & 17/08/2020. |
Non-toxic prefeed application in the western portion of the Aorere project area was completed 04/08/2020. 1080 application in the western portion of the Aorere project area was completed on 16/08/2020 & 17/08/2020. |
2020/21 St Arnaud Aerial
Client: Department of Conservation
Status: 1080 application in the St Arnaud project area was completed on 08/09/02020. |